Bhubaneswar: In a major step for the Khurda Road-Balangir Rail Line Project, engine rolling and testing on newly laid train line between Jharmunda and Boudh stations over a distance of 16.270 kilometers was completed successfully by Commissioner of Railway Safety (CRS).

This achievement marks a critical milestone in the construction of the much-awaited railway line that is poised to significantly improve connectivity in remote regions of Odisha, East Coast Railway (ECoR) said in a press release on Thursday.

Apart from this, construction work between Boudh-Champapur Rail section, a distance of 13.701 kms and Champapur-Purunakatak, a distance of 13.437 kms is also going on full swing, demonstrating steady progress in the overall project. To ensure faster completion, construction efforts are being undertaken from both ends simultaneously, highlighting the commitment to meet the ambitious deadlines for this vital infrastructure initiative.

The Khurda Road-Balangir Rail Line is an extensive project spanning 301 kilometers, and to date, 199 kilometers have been commissioned, including 106 kilometers from Khurda Road to Daspalla and 93 kilometers from Balangir to Boudh. Another 27 kms from Boudh to Purunakatak is being developed in full swing and is about to complete soon. The remaining 75 kilometers from Purunakatak to Daspalla, which passes through challenging jungle and sanctuary areas involving tunnel construction, is progressing and will be completed in due course.

This railway project holds great significance for enhancing transportation and economic development in remote areas, with the Ministry of Railways closely monitoring the project’s advancement to ensure timely commissioning. Despite facing formidable engineering challenges, particularly in tunnel construction through rugged terrain, the project continues to achieve major milestones.

The Khurda Road-Balangir Rail Line is not only crucial for improving connectivity but also stands as a testament to Indian Railways’ ability to overcome some of the most complex engineering challenges ever encountered in railway construction. Successful completion of the tunnels will be a major breakthrough, underscoring Indian Railways’ commitment to delivering critical infrastructure in even the most remote regions of the country.

After successful inspection of safety aspects of the newly laid Jharmunda & Boudh Railway section, this line has been authorised by the CRS for running of train traffic. However, train services will have commenced in this section after completion of other infrastructural and passenger amenities work. A light engine trial run has already been conducted.

This remarkable progress on the rail line brings the region one step closer to enhanced connectivity and new avenues for economic growth.

OB Bureau

Recent Posts

Imtiaz Ali’s U-Turn About Firing Crew Member To Ensure Alia Bhatt’s Safety On ‘Highway’ Sets

Mumbai: Hours after stating that he had to fire a crew member on the sets…

November 23, 2024

Maharashtra Polls: Swara Bhasker Alleges EVM Manipulation After Husband Fahad Loses Close Contest

Mumbai: In keeping with the trend across Maharashtra, the Mahayuti coalition’s candidate won the Anushakti…

November 23, 2024

Bassist Mohini Dey Breaks Silence On AR Rahman Link-Up Rumours

Mumbai: Celebrated musician AR Rahman’s grey divorce, after 29 years of marriage to Saira Banu,…

November 23, 2024

Odisha Cabinet Approves Proposal To Amend Universities Act To Ensure Transparency, Autonomy

Bhubaneswar: In a significant step towards strengthening higher education, the state Cabinet on Saturday approved…

November 23, 2024

America Moving Towards Bankruptcy, Warns Elon Musk; Why Is He Saying So?

New York: As talk about the United States of America’s (USA) mounting debts are doing…

November 23, 2024

Jharkhand Polls: Odisha Guv Raghubar Das’ Daughter-In-Law Reclaims Home Turf

Rachi/Bhubaneswar: Odisha Governor Raghubar Das’ daughter-in-law Purnima Das Sahu has won from Jamshedpur East Assembly…

November 23, 2024

Perth Test: Jaiswal (90*), Rahul (62*) Put India On Top As 3 Wkts Fall On Day 2 After 17 On First Day

Perth: Openers Yashasvi Jaiswal (batting 90) and KL Rahul (batting 62) put up a stellar…

November 23, 2024

2 Maoist Dumps Busted, Explosives & Other Articles Seized In Odisha’s Boudh

Boudh: In a major success in anti-naxal operation, security personnel have unearthed two Maoist dumps…

November 23, 2024