Sonepur: The much awaited Khurda-Balangir railway line in Odisha moved a step ahead with trial run of a train between two stations in Subarnapur district.
According to sources, the project work from Balangir had been completed upto Jhartarbha railway station. The trial run of a train had also been conducted upto Jhartarbha last month.
The project further progressed with railway tracks laid from Jhartarbha to Khambeswaripali. On Thursday, MK Choudhury, PCMD, South Eastern Railway inspected the trial run of the train from Jhartarbha to Khambeswaripali.
It may be noted that the broad gauge rail line of around 10.65 km between Bichhupali and Jhartarbha of the project was commissioned on November 13 last year.
The Commissioner of Railway Safety (CRS) had given its content after inspecting the new rail line on November 10 and declared the 289-km rail line of the project as fit for commissioning. So far, 115.65 km of rail line work of the total project has been commissioned.
Bhubaneswar: The Odisha government has asked ineligible beneficiaries to surrender their ration cards acquired through…
Bhubaneswar: The heritage temple tanks, ponds and wells in the Old Town area of Bhubaneswar…
Chennai: After the tragic death of 27-year-old Tamil Nadu entrepreneur Jayesh Ram, Zoho CEO Sridhar…
Bhubaneswar: Income Tax (I-T) department officials continued their raid for the fourth day on Monday…
Kolkata: Sealdah Civil and Criminal Court on Monday sentenced Sanjay Roy to life imprisonment for the…
Kolkata: Ahead of pronouncement of the quantum of punishment, R G Kar rape-murder convict Sanjay…
This website uses cookies.