Power Ministry Cites Heavy Rain, Economic Revival & Other Reasons For Coal Crisis

New Delhi/Bhubaneswar: Even as coal shortage in the country took its first casualty with Punjab State Power Corporation Ltd (PSPCL) cutting down power generation, the Power Ministry has cited the reasons for the crisis.

Admitting the problem, the ministry said as on October 3, the average stock of coal in power plants was for about four days. In a release, the ministry cited following four reasons for the depletion of coal stocks at the power plants:

  • Unprecedented increase in demand for electricity due to the revival of the economy
  • Heavy rains in coal mine areas during September 2021 thereby adversely affecting the coal production as well as despatch of coal from mines
  • Increase in prices of imported coal to unprecedented high level leading to more dependence on domestic coal and a substantial reduction in power generation
  • Lack of adequate coal stocks before the onset of Monsoon

The ministry also said there were heavy dues of coal companies in states of Maharashtra, Rajasthan, Tamil Nadu, Uttar Pradesh, Rajasthan and Madhya Pradesh.

Meanwhile, the Core Management Team (CMT) formed by the Ministry of Power  is closely monitoring the coal stock on daily basis to ensure follow-up actions with Coal India Ltd (CIL) and Indian Railways to improve the supply to power plants. The team comprises representatives of MOP, CEA, POSOCO, Railways and CIL.

The ministry said as on October 7, the total dispatch of coal by CIL was 1.501 MT thereby reducing the gap between consumption and actual supply.

The Ministry of Coal and CIL have assured that they are taking steps to increase dispatch to the power sector to 1.6 MT per day in the next three days and thereafter try to touch 1.7 MT per day.

In Punjab, as the thermal power plants are left with coal stock for upto five days, they have cut down the power generation. On Friday, the power plants had received some coal supply to run their operations, he added.

Though the Punjab State Power Corporation Ltd (PSPCL) officials claimed minimal load shedding, power-cuts for two-three hours have been reported at many places in the state.

Also ReadCoal Crisis: Ministry Assures Of Increasing Supply To Power Industries In 3 Days

Also ReadCoal Shortage: Power Cuts Imposed In Punjab, Delhi Too In Dire Straits

OB Bureau
Share
Published by
OB Bureau

Recent Posts

Night Temp May Rise To 23°C In Bhubaneswar; Dense Fog Alert For 15 Odisha Dists

Bhubaneswar: The night temperature may rise to 23 degree Celsius in Odisha with the India… Read More

2 minutes ago

Padma Honour For Icons In Art, Medicine, Dance & Literature From Odisha

Bhubaneswar: This year’s Padma awardees from Odisha embody the spirit of state's rich cultural heritage… Read More

1 hour ago

BJD Dissolves Its State-Level Frontal Organisations After Appointing Returning Officer For Polls

Bhubaneswar: The Biju Janata Dal (BJD) has dissolved its state-level frontal organisations, including women, youth,… Read More

3 hours ago

On Camera, Masked Robber Strikes At Odisha Ex-Congress Chief’s Residence In Bhubaneswar

Bhubaneswar: An unidentified miscreant allegedly looted cash and gold ornaments worth over Rs 30 lakh… Read More

3 hours ago

One Dead, Several Injured As Van Carrying Students To R-Day Parade Overturns In Odisha

Cuttack: One person died while several others were injured when a pick-up van transporting school… Read More

4 hours ago

Here Is Why President Unfurls National Flag On Republic Day; What’s Special This Year

New Delhi: President Droupadi Murmu will lead the nation in celebrating Republic Day from Kartavya… Read More

5 hours ago