TPSODL Sets Up 33-KV Line To Improve Power Supply During Heatwave In Odisha’s Rayagada

Berhampur: In order to ensure reliable and quality power supply during the ongoing heatwave, Tata Power Southern Odisha Distribution Limited (TPSODL) has set up a new 33 kv line from the Gunupur grid substation to Bikrampur primary substation in Odisha’s Rayagada district.

The newly installed 33 kv line extends 9 km from Gunupur grid substation to Bikrampur substation. Previously, the Bikrampur primary substation received its power supply through a 33-kv feeder that stretched 27 km from the Akhusingi grid substation. This long feeder and old conductor caused frequent power supply issues.

With the new line in place, approximately 7 panchayats and 87 villages, serving 4,670 consumers under the Bikrampur primary substation, will benefit from a more reliable and quality power supply, said the company in a press release on Saturday.

The areas now receiving improved power supply include Jagannathpur, Gotalpadar, Morama, Sirijholli, and Bagasala panchayats of Gunupur block, besides Gulumunda and Ukamba panchayats of Ramanaguda block. This new infrastructure has resolved previous issues of low voltage and power interruptions.

“We are committed to providing reliable and quality power to our consumers. The new 33 kv line from Gunupur to Bikrampur is a significant step in that direction. This upgradation will ensure that the residents of these areas have a consistent power supply. We will continue to invest in infrastructure improvements to serve our communities better,” said Amit Kumar Garg, CEO of TPSODL.

Get real time updates directly on you device, subscribe now.