New Delhi: The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, has approved the development of a Second Container Terminal at Kamarajar Port Limited (KPL) at an estimated Public-Private Partnership (PPP) cost of Rs 4,288.26 crore, including GST. Executed on a Design, Build, Finance, Operate, and Transfer (DBFOT) basis over a 40-year concession period, the project entails zero financial outlay for the Union government.
Chosen through open global bidding, the private concessionaire will finance the entire PPP component—Rs 2,429.32 crore for Phase I and Rs 1,858.94 crore for Phase II—and recover its investment via user charges. KPL will separately bear an estimated Rs 450 crore toward dredging. Environmental and statutory clearances will be secured before the bid due date.
Project Specifications and Timeline
The 900-metre-long, 30-metre-wide terminal will feature an 18-metre design draft, enabling it to berth large mainline vessels up to 400 metres long with capacities of 24,346 Twenty-foot Equivalent Units (TEUs). It will add 2.0 million TEUs in annual capacity across two stages:
Phase I (1.1 million TEUs): Construction will conclude within 24 months of the concession award, starting commercial operations in the 25th month.
Phase II (0.9 million TEUs): Construction will run from the 25th to the 48th month, with full commercial operations beginning in the 49th month.
Capacity Need and Economic Impact
Wholly owned by the Chennai Port Authority under the Ministry of Ports, Shipping and Waterways, KPL (formerly Ennore Port Limited) is one of India’s 12 Major Ports. In FY 2025–26, KPL posted Rs 1,280 crore in revenue and Rs 924 crore in profit before tax, handling 49.08 million tonnes of cargo and 1,008 vessels. Its existing 0.8 million TEU terminal operated at roughly 88% capacity, handling over 0.7 million TEUs. Over the past five years, KPL’s overall cargo and container traffic grew at compound annual growth rates of 13.64% and 9.9%, respectively, outpacing the national container growth rate of 7%.
Aligned with Maritime India Vision 2030, Maritime Amrit Kaal Vision 2047, and Atmanirbhar Bharat, the terminal will facilitate direct mainline vessel calls and lower feedering costs via foreign hubs. It will boost export-import logistics for automotive, electronics, engineering, and chemical sectors across Tamil Nadu, Karnataka, Andhra Pradesh, and Telangana, while generating roughly 750 jobs during construction and 800 during operations.