NGT Slaps Rs 25 Cr Penalty On Vedanta For Violating Environmental Norms

Bhubaneswar: A fine of Rs 25 crore has been imposed on Vedanta Limited for violating environmental norms by way of expanding its plant at Lanjigarh in Kalahandi district.

A special bench of National Green Tribunal (NGT) chairperson Adarsh Kumar Goel imposed the fine while hearing an appeal against the environmental clearance granted to Vedanta Limited (formerly Sesa Sterlite Ltd.), Bhubaneshwar (November 20, 2015), for expansion of Alumina Refinery and Captive Power Plant at Lanjigarh.

“In the present case, the prosecution has been initiated for illegal expansion. Liability for compensation on the polluter pays principle is assessed at Rs 25,00,00,000 (Rupees twenty five crore only) having regard to the clear violation and financial capacity of the unit to be used for the restoration of the environment in terms of the environment plan to be prepared and executed as per the direction in later part of this order,” said NGT in its May 2 order.

The company has been directed to deposit the amount with State Pollution Control Board within one month. The money will have to be kept in a separate account and utilised for restoration of environment, the order stated.

Though the company argued that it has invested Rs 50,000 crore and has undertaken all mitigation measures for the protection of the environment, the green court held the company accountable for the violation of a partly undertaken expansion without prior environmental clearance from Ministry of Environment, Forest and Climate Change (MoEF&CC).

The other main issue was of the drawal of water from River Tel. Though it is stated that the drawal of water may not affect the flow of the river, considering the increasing need for water from the river not only by the PP but also by others, permissibility of drawal of water should not remain static and unconditional forever, the NGT noted.

Further, the tribunal said its impact should be considered from time to time and the provision by way of additional conditions made to safeguard this aspect.

Accordingly, the green court also constituted a Committee comprising of the Secretary, Irrigation Department, Orrisa, Central Water Commission, State PCB and Regional Offices of MoEF&CC and CPCB in the matter. The panel has to formulate additional conditions based on periodical impact assessments within three months, it directed.

Get real time updates directly on you device, subscribe now.

Comments are closed.